Blue River South
Blue River South
Kansas City, Missouri
Areas 1 & 2
$8,325,000
ENGINEER GBA
CONTACT Lisa Walters and Doug Martin, GBA
This was a comprehensive I & I reduction project. The rehab included:
- 750 LF of open-cut point repairs
- 3,300 LF of complete mainline segment removal and replacement via pipe bursting
- 80 EA open-cut lateral connection repairs
- 650 EA trenchless lateral connection repairs
- 1,600 LF of open-cut lateral replacement (including pipe bursting)
- 14,300 LF lateral CIPP
- 45,000 LF of mainline CIPP
- 280 EA manhole casting replacementsKANSAS CITY, MISSOURI
- 3,700 VF cementitious manhole lining and associated manhole rehab
- 500 EA CIPP end seals
- Extensive CCTV inspections